1. Contract Execution Alignment with Agreed Terms
a. Contract Familiarization
Immediately after awarding a contract, SayPro and the vendor jointly review the contract terms to ensure mutual understanding. This includes:
- Scope of work
- Delivery timelines
- Performance standards and KPIs
- Payment terms and conditions
- Compliance requirements (legal, regulatory, and SayPro-specific)
b. Detailed Work Plan Submission
Within five working days of contract signature, vendors are required to submit a Detailed Work Plan which breaks down:
- Key deliverables and associated deadlines
- Resource allocation and team structure
- Risk mitigation strategies
- Communication protocols
SayPro reviews and approves the plan, establishing it as a baseline for performance monitoring.
c. Performance Monitoring Agreement (PMA)
The vendor signs a PMA that outlines the monitoring frequency, documentation expectations, and consequences for deviation from agreed terms.
2. Ensuring Timely Delivery of All Contractual Outputs
a. Timeline Tracking and Milestone Management
SayPro uses a centralized Contract Tracking Dashboard to monitor all active contracts. This includes:
- Milestone-based tracking of deliverables
- Visual alerts for upcoming, delayed, or missed deadlines
- Integration with vendor-submitted progress reports
b. Monthly Vendor Progress Reports
Vendors submit Monthly Progress Reports that detail:
- Deliverables completed to date
- Tasks in progress and upcoming deadlines
- Challenges faced and mitigation actions taken
- Any deviation from original timelines and justifications
These are reviewed during monthly Performance Review Meetings.
c. Performance Scorecards
Each vendor receives a monthly scorecard that scores them on:
- Timeliness
- Quality of deliverables
- Communication and responsiveness
- Compliance with contract terms
Vendors scoring below threshold are flagged for remedial action.
3. Real-Time Monitoring and Verification
a. Field Verification
Where applicable, SayPro field teams conduct verification visits to validate the delivery of services or goods.
b. Digital Proofs and Milestone Evidence
Vendors are required to submit:
- Time-stamped photos/videos
- Delivery receipts
- Signed beneficiary feedback forms (where applicable)
c. Stakeholder Feedback Collection
Feedback from project teams or service recipients is gathered periodically to confirm whether deliverables meet quality and functional expectations.
4. Non-Compliance Management and Corrective Action
a. Early Warning System
Vendors falling behind schedule are flagged, and SayPro issues a Performance Alert.
b. Corrective Action Plan (CAP)
The vendor must submit a CAP detailing how they will address delays or deviations. Weekly check-ins are instituted until the contract is back on track.
c. Escalation and Penalties
Continued non-performance leads to:
- Financial penalties as per contract terms
- Potential partial or full termination of contract
- Disqualification from future tenders for a defined period
5. Final Contract Review and Closeout
At the end of each contract:
- A Close-Out Report is produced, confirming whether all deliverables were met on time and in accordance with agreed terms.
- Vendors undergo a Final Evaluation, which is recorded in the SayPro Preferred Vendor Registry for future reference.
- Lessons learned and performance insights are compiled to improve future procurement cycles.
6. Continuous Improvement and Feedback Loop
Findings from ongoing performance monitoring are used to:
- Refine procurement procedures and timelines
- Enhance vendor prequalification criteria
- Improve contract template language for clarity and enforceability
- Update the SCMR framework with performance trends and outcomes
Conclusion
By embedding robust performance monitoring mechanisms, SayPro ensures that all vendors awarded under the January SCMR-1 contract cycle are held to the highest standards. Contracts are not just signed—they are actively managed and executed in full alignment with the agreed terms, with clear accountability and measurable results.